Energy Center 1
Fuel Type: Natural Gas
Capacity: 75 MW
Fuel Type: Natural Gas
Capacity: 75 MW
Fuel Type: Coal-Fired Steam Plant
Capacity: 35-100 MW
Fuel Type: Natural Gas
Capacity: 60 MW
Fuel Type: Coal
Capacity: 100 MW
Fuel Type: Slice of the System
Capacity: 60 MW
Fuel Type: Diesel
Capacity: 10 MW
Fuel Type: Solar
Capacity: 86 MW
Fuel Type: Hydropower
Capacity: 32 MW
KYMEA is developing the 75 MW Energy Center I power plant in Madisonville, Kentucky. The facility will consist of four Wärtsilä 18V50SG reciprocating internal combustion engine generators, each with a nominal output capacity of 18.8 MW. Designed for both continuous and peaking service, the plant will support the Agency’s power supply portfolio with flexible natural gas generation. Construction began in April 2025, and commercial operation is currently planned for summer 2027.